Holdrege Grandstand & Music Rooms Renovation
A complex renovation delivered on schedule through proactive planning, disciplined project management, and trusted collaboration.
OWNER:
Holdrege Public Schools,
Holdrege, NE
ARCHITECT:
Wilkins Architecture
LOCATION:
Holdrege, NE
ORIGINAL CONTRACT VALUE:
$1,755,433 (approx. $2,457,000 in 2026 dollars*)
FINAL CONTRACT VALUE:
$1,758,037 (approx. $2,461,000 in 2026 dollars*)
COMPLETED:
August 2020
DELIVERY METHOD:
General Contracting
REFERENCE:
Todd Hilyard, Superintendent
*2026 dollar equivalents estimated using approximately 40% cumulative nonresidential construction cost inflation from 2020 to 2026, per Construction Analytics and Mortenson Cost Index data.

PROJECT OVERVIEW
From Planning to Successful Delivery
This project involved a full renovation of an existing athletic grandstand complex and music room facilities for Holdrege Public Schools. RMV served as the general contractor, managing a compressed schedule that demanded precise coordination across multiple trade scopes in an active school environment.
Scope included renovation of 3,800 SF of interior music room space and full demolition and replacement of the existing athletic grandstand with a new 1,500-seat prefabricated structure and press box, delivered over a single summer school break window.
The project was completed during a period of significant disruption. COVID-era supply chain constraints created material availability challenges throughout the construction window, and a major rain event required emergency soil remediation mid-project. RMV managed both without a schedule extension and delivered final completion in August 2020 within $2,604 of the original contract value.
That near-zero variance between the original and final contract value on a project complicated by a pandemic and a weather emergency is not an accident. It reflects the discipline RMV brings to every project from the day preconstruction begins.

WHY IT MATTERS
WHY THIS PROJECT IS RELEVANT
This project demonstrates what RMV does when conditions change and the schedule cannot. A pandemic, a weather emergency, and a compressed summer school deadline, all on a single project. RMV delivered on time and within $2,604 of the original contract value. That is not a coincidence. It is the result of preconstruction discipline, proactive communication, and a team that does not look for reasons a project cannot be done.
$ 2,604
Variance between original and final contract value on a COVID-era project with a major weather event

EXPLORE MORE
Similar Projects
Education Project • Kearney, NE
CCC Welding Technology
Education Project • Minden, NE
Minden Public Schools
Healthcare • 60+ Projects
Good Samaritan Society

Ready to Build Your Next Success Story?
Whether you're planning a new facility or a complex renovation, RMV Construction is ready to help you move forward with confidence.